Regasification plant unavailability annual maintenance

UMM event details

  • UMM event publish date: 30-07-2020 03:07:31
  • UMM event URL:
  • Messages attached: 5

Message 20200803-P-YGC-IPLAN00001_001 Type II

Message data

  • Message ID: 
    20200803-P-YGC-IPLAN00001_001
  • Event Status: 
    Active
  • Type of Unavailability: 
    Planned
  • Type of Event: 
    Regasification plant unavailability
  • Unit of measurement: 
    GWh/d
  • Unavailable capacity: 
    112
  • Available capacity: 
    0
  • Technical capacity: 
    112
  • Reason for the unavailability: 
    Unavailability of REGANOSA Mugardos LNG Terminal due to planned maintenance.
  • Balancing Zone: 
    21Y---A002A005-T
  • Affected Asset: 
    21W0000000000338
  • Market Participant: 
    Regasificadora del Noroeste S.A.
  • Event Start: 
    03-08-2020 07:08:00
  • Event Stop: 
    03-08-2020 19:08:00
  • Remarks: 
    On the occasion of the execution of planned maintenance, Reganosa foresees the unavailability of the emission to the transport network, truck loading and loading and unloading vessels.

Message 20200803-P-YGC-IPLAN00002_001 Type II

Message data

  • Message ID: 
    20200803-P-YGC-IPLAN00002_001
  • Event Status: 
    Active
  • Type of Unavailability: 
    Planned
  • Type of Event: 
    Regasification plant unavailability
  • Unit of measurement: 
    GWh/d
  • Unavailable capacity: 
    112
  • Available capacity: 
    0
  • Technical capacity: 
    112
  • Reason for the unavailability: 
    Unavailability of REGANOSA Mugardos LNG Terminal due to external electrical supply maintenance.
  • Balancing Zone: 
    21Y---A002A005-T
  • Affected Asset: 
    21Z000000000126X
  • Market Participant: 
    Regasificadora del Noroeste S.A.
  • Event Start: 
    04-08-2020 07:08:00
  • Event Stop: 
    04-08-2020 19:08:00
  • Remarks: 
    On the occasion of the execution of repair works in the electrical connection that supplies the Mugardos regasification plant, Reganosa foresees the unavailability of the emission to the transport network, truck loading and loading and unloading vessels.

Message 20200803-P-YGC-IPLAN00003_001 Type II

Message data

  • Message ID: 
    20200803-P-YGC-IPLAN00003_001
  • Event Status: 
    Active
  • Type of Unavailability: 
    Planned
  • Type of Event: 
    Regasification plant unavailability
  • Unit of measurement: 
    GWh/d
  • Unavailable capacity: 
    112
  • Available capacity: 
    0
  • Technical capacity: 
    112
  • Reason for the unavailability: 
    Unavailability of REGANOSA Mugardos LNG Terminal due to external electrical supply maintenance.
  • Balancing Zone: 
    21Y---A002A005-T
  • Affected Asset: 
    21Z000000000126X
  • Market Participant: 
    Regasificadora del Noroeste S.A.
  • Event Start: 
    05-08-2020 07:08:00
  • Event Stop: 
    05-08-2020 19:08:00
  • Remarks: 
    On the occasion of the execution of repair works in the electrical connection that supplies the Mugardos regasification plant, Reganosa foresees the unavailability of the emission to the transport network, truck loading and loading and unloading vessels.

Message 20200803-P-YGC-IPLAN00004_001 Type II

Message data

  • Message ID: 
    20200803-P-YGC-IPLAN00004_001
  • Event Status: 
    Active
  • Type of Unavailability: 
    Planned
  • Type of Event: 
    Regasification plant unavailability
  • Unit of measurement: 
    GWh/d
  • Unavailable capacity: 
    112
  • Available capacity: 
    0
  • Technical capacity: 
    112
  • Reason for the unavailability: 
    Unavailability of REGANOSA Mugardos LNG Terminal due to external electrical supply maintenance.
  • Balancing Zone: 
    21Y---A002A005-T
  • Affected Asset: 
    21Z000000000126X
  • Market Participant: 
    Regasificadora del Noroeste S.A.
  • Event Start: 
    06-08-2020 07:08:00
  • Event Stop: 
    06-08-2020 19:08:00
  • Remarks: 
    On the occasion of the execution of repair works in the electrical connection that supplies the Mugardos regasification plant, Reganosa foresees the unavailability of the emission to the transport network, truck loading and loading and unloading vessels.

Message 20200803-P-YGC-IPLAN00005_001 Type II

Message data

  • Message ID: 
    20200803-P-YGC-IPLAN00005_001
  • Event Status: 
    Active
  • Type of Unavailability: 
    Planned
  • Type of Event: 
    Regasification plant unavailability
  • Unit of measurement: 
    GWh/d
  • Unavailable capacity: 
    112
  • Available capacity: 
    0
  • Technical capacity: 
    112
  • Reason for the unavailability: 
    Unavailability of REGANOSA Mugardos LNG Terminal due to external electrical supply maintenance.
  • Balancing Zone: 
    21Y---A002A005-T
  • Affected Asset: 
    21Z000000000126X
  • Market Participant: 
    Regasificadora del Noroeste S.A.
  • Event Start: 
    07-08-2020 07:08:00
  • Event Stop: 
    07-08-2020 19:08:00
  • Remarks: 
    On the occasion of the execution of repair works in the electrical connection that supplies the Mugardos regasification plant, Reganosa foresees the unavailability of the emission to the transport network, truck loading and loading and unloading vessels.